Powercor - REFCL Design Program
Peracon worked for Powercor on their REFCL program of works for over 3 years. Peracon had 7 employees working in the Powercor team on a secondment basis.
Peracon’s roles included the following:
- Primary design manager,
- Primary engineer,
- Civil engineer,
- Primary designers, and
- Secondary designer.
Peracon assisted Powercor to keep the challenging REFCL project on schedule, which included the following sites:
- Tranche 1 - Eaglehawk
- Tranche 2 - Ballarat North, Ballarat South, Charlton, Bendigo Terminal station, Terang & Ararat
- Tranche 3 - Koroit & Hamilton
Benefits:
Peracon were able to mobilise quickly to provide Powercor with an experienced design team to meet the tight regulatory schedule. Our experienced team of engineers and designers were embedded in the project team and worked closely with the Powercor staff to deliver this programme of works.